Main Supplies already made:


Replacement of the protections of the groups and auxiliary services, including studies and design, as well as the supply and assembly of all the Measure Transformers and Electrical Cables of the installation at the Salamonde Central.
.............................................................

Provision of services for the design and commissioning of GE protections for the Fragilde Plant and EDA Substations.
.............................................................

Replacement of protections for groups and auxiliary services, including studies and design, as well as the supply and assembly of all measurement transformers and electrical cables in the installation, at CPPE's Central de Tabuaço of the Hydraulic Production Department.
.............................................................

Supply, assembly and commissioning of the bar protections of Riba D`Ave Substation by REN.
.............................................................

Supply, assembly and commissioning tests for protections in 3 Hydro Power Plants of E.E.M.
.............................................................

Improvement of Alternators in Groups 1, 2 and 3 of the Miranda Hydroelectric Power Plant of CPPE - Hydraulic Production.
.............................................................

Supply, assembly and commissioning of two (2) 220KV Line protection systems and two (2) 220KV Interbar / Bypass protection systems from Valdigem Substation from REN - Rede Eléctrica Nacional's.
..............................................................

Improvement of the Turbines of Groups 1, 2 and 3 of the Fratel Hydroelectric Power Plant of CPPE - Hydraulic Production.
.............................................................

Improvement of the Turbines of Groups 1, 2 and 3 and the Alternators of Groups 1 and 2 of the Castelo do Bode Hydroelectric Power Plant of CPPE - Hydraulic Production.
.............................................................

Improvement of Turbines and Alternators in Groups 1 and 2 of the Caniçada Hydroelectric Power Plant of CPPE - Hydraulic Production.
.............................................................

Repair of the Mechanical Organs of Group 2 of the Alto Rabagâo Hydroelectric Power Plant of EDP / CPPE - Hydraulic Production.
.............................................................

Improvement of Turbines and Alternators in Groups 1, 2, 3 and 4 of the Belver Hydroelectric Power Plant of EDP Produção EM.
.............................................................

Supply and commissioning tests for the protections of the Alternators / Transformers Groups of the 1st and 2nd Step of EDIA's Alqueva Central.
.............................................................

Supply, parameterization and commissioning tests for protections for several Wind Farms such as: Lomba da Seixa, Snr.ª da Vitória, Archeira, Amêndoa, Escusa, Teixeiró, Castanheira, Chão Falcão, Achada, Arcela and S. Mamede.
.............................................................

Supply, parameterization and commissioning tests for protections for several cogenerations such as: Hospital Pedro Hispano - Matosinhos, Hospital Garcia da Horta - Lisbon, Hospital de São Francisco Xavier - Lisbon.
.............................................................

Supply, parameterization and commissioning tests of protections for several Mini-Hydro such as: Vila Cova, Sabugueiro, Rabaçal.
.............................................................

Supply, transport, assembly and commissioning of 400 KV Armored SDS (Disconnect-Breaker-Disconnect) Blocks destined for the Batalha Substation of REN - Rede Eléctrica Nacional.
.............................................................

Supply, Assembly, Parameterization and Tests for putting Protections into service in several EDP Distribuição Substations.
.............................................................

Electrification of the Mechanical Organs of Groups 1 and 2 of the Alto Rabagão Plant.
.............................................................

Project and Electrification of all Mechanical Organs in Groups 1 and 2 of the Cabril Central..
.............................................................

Electrification of the Mechanical Organs of Groups 1 and 2 of the Bouçã Central.
.............................................................

Replacement of the Protections of Groups 1, 2 and 3 and Auxiliary Services of Central of Carrapatelo.
.............................................................

Replacement of the Protection of the Auxiliary Services of the Central of Pocinho.
.............................................................

Supply and Commissioning of Protections for Petrogal at Sines through Efacec.
.............................................................

Renovation works for Protection Systems (SP) of EDP Distribuição substations including equipment supply, project, parameterization and commissioning, namely for the Guimarães, Ruivães, Bustos, Trancoso, Condeixa, Alvelos ; Mortágua, Várzea and Arouca.
.............................................................

Supply of a Protection System for the Groups of the Alqueva II Plant, EDP Prodution, including duly closed and tested cabinets, parameterization of protections and commissioning.